Royal ISD hired E3 to undertake a district-wide energy efficiency and facility upgrade project. Royal ISD was facing many of the same problems that other districts face; high energy bills, constant problems with their energy management controls, chillers malfunctioning and widespread comfort complaints. Together E3 and Royal ISD crafted a plan that would address each one of these issues while saving the district’s precious MandO dollars in the process.

Royal ISD
Project ScopeEnergy Efficiency and Facility Upgrade
Contract Amount$10,453,331
Annual Savings
MarketK-12

The following projects were initiated to solve the issues:

  • Chiller Installation: 7 new chillers throughout the district
  • Plant Redesign: Chiller plant redesign and replacement
  • Air Handling: RTU and DOAS redesign and replacement
  • AHU Upgrade: AHU Replacement
  • LED Retrofit: District-wide LED retrofit
  • BAS Expansion: Installation and expansion of the Building Automation System
  • Component Replacement: Replace control valves and dampers throughout the district
  • Surge Protection: Surge Protection
  • UPS Installation: Uninterruptible Power Supply (UPS) installation

Results

The result of the project was dramatically reduced utility bills, fewer comfort complaints and maintenance calls, and a huge swipe out of their deferred maintenance. Additionally, this project will result in rebate incentives from CenterPoint Energy.

Installation and Construction Progress

A look at the mechanical modernization and installation process, showcasing the equipment upgrades and on-site construction work in progress across the facilities.

Completed Improvements and Retrofits

The finalized upgrades, featuring high-efficiency systems and optimized building environments designed to deliver maximum energy performance and operational savings.

Additional Project Details

Visual details and close-up views showing the technical scope and facility components addressed during the project execution.